DERSA (Government of the State of São Paulo)Em alto-mar
Client: DERSA - Road Development S/A (Government of the State of São Paulo)
Location: Iguape, São Paulo
Period: April to October 2011 (6 months)
Category: NAVAL / OFFSHORE
Contact Us
The Engport Group was hired by DERSA to carry out the complete structural refurbishment of Ferry FB-16, one of the most important vessels in the Coastal Crossings System of the State of São Paulo. This ferry operates on the strategic Cananéia/Ilha Comprida Crossing in the South Coast, transporting thousands of vehicles and tourists monthly.
THE COASTAL CROSSINGS SYSTEM
Since 1989, DERSA has been managing the Coastal Crossings System of the State of São Paulo, consisting of eight critical crossings connecting islands and the mainland along the entire coast of São Paulo. The FB-16 is a ferryboat with the capacity to transport approximately 20-25 vehicles per trip, operating 24 hours a day, 7 days a week.
The Cananéia/Ilha Comprida Crossing is particularly critical: the only direct connection between the mainland and Ilha Comprida, a tourist region with 110 kilometers of preserved coastline, beaches, and UNESCO-listed Atlantic Forest. During the high season (December to March), the traffic reaches over 1,000 vehicles per day.
THE CRITICAL CONTEXT
In 2011, after years of uninterrupted operation exposed to the extremely aggressive marine environment of the Cananéia Channel (brackish water, constant salt spray, tidal cycles), the FB-16 showed severe structural compromise:
Hull plating with advanced corrosion (perforations and thinning)
Oxidized internal structures
Imminent risk of closure by the Port Captaincy
Urgent need for refurbishment before the summer high season
DERSA made the strategic decision: complete and emergency refurbishment of the vessel to return it to operation as quickly as possible, minimizing the impact on the crossing.
THE CHALLENGE: MARITIME ENVIRONMENT WORK
Refurbishing a large vessel in Iguape, near the Cananéia Channel, presented unique challenges:
Remote location: Over 200 km from São Paulo, complex logistics
Aggressive environment: Outdoor work, salt spray, frequent rains
Tight deadline: 6 months for complete refurbishment
High visibility work: Ferry out of operation impacting thousands of users daily
Public pressure: Local press coverage, residents demanding return
EXECUTION METHODOLOGY
Our team developed a detailed plan to maximize efficiency:
PHASE 1 - DIAGNOSIS AND PREPARATION (1 MONTH):
Complete inspection of the hull and superstructure
Mapping of all compromised areas
Specification of materials (plates, profiles, consumables)
Logistics for transporting heavy materials to Iguape
Mobilization of team and equipment
PHASE 2 - REMOVAL OF COMPROMISED PLATING (1 MONTH):
Team of 20 professionals working simultaneously:
Oxy-fuel cutting of all oxidized plating
Removal of compromised internal structures
Complete cleaning of affected areas
Surface preparation for new plates
Special challenge: Hot cutting in a maritime environment with high humidity and constant natural ventilation. Need for wind protection to ensure quality cuts.
PHASE 3 - MANUFACTURING AND INSTALLATION OF NEW PLATING (4 MONTHS):
The most complex and labor-intensive phase:
Manufacturing:
Cutting naval steel plates ASTM A36 with exact dimensions
Forming (rolling when necessary)
Preparation of bevels for welding
Pre-assembly on land
Installation:
Hoisting and positioning of large plates (up to 500 kg each)
Structural welding with coated electrode E7018
Fillet and butt welds as per naval project
100% visual inspection of welds
Non-destructive testing on critical welds (penetrant liquid)
Welding Team:
Qualified welders in naval welding
SMAW processes (shielded metal arc welding)
Inspection by certified level 2 professional
PHASE 4 - COMPLETE PAINTING OF THE VESSEL (1 MONTH):
Anticorrosive painting system for a marine environment:
Surface preparation:
Mechanical sanding of all metal surfaces
Removal of mill scale
Cleaning with solvent
Complete drying
Paint application:
Anticorrosive epoxy primer (2 coats)
Intermediate epoxy paint (2 coats)
Finish with synthetic nautical enamel (2 coats)
Total system: 6 coats, controlled DFT (thickness)
Colors:
Hull: DERSA Standard (yellow and white)
Safety markings as per Navy regulations
Applied FB-16 numbering
TIME PRESSURE
Like all critical public infrastructure projects, the pressure was constant:
Users: Thousands of residents and tourists depended on the crossing
Press: Local newspaper reporting weekly progress
DERSA: Internal demand for return to operation
Government: Project monitored by state representatives
Additionally, the region's unstable weather (frequent rains, strong winds) delayed welding and painting work, requiring constant replanning.
HSE MANAGEMENT IN NAVAL ENVIRONMENT
Work on vessels requires special attention to safety:
Work at height (upper deck, 4-5 meters)
Confined spaces (inside the hull)
Hot work (welding and cutting) with fire risk control
Specific personal protective equipment (flame-retardant uniforms)
Training NR-34 (Hot Work) and NR-33 (Confined Space)
Emergency and rescue plan
EARLY DELIVERYOCTOBER 5, 2011 - 5 days AHEAD of schedule:
✅ Entire metal structure recovered
✅ New plating installed
✅ Complete painting finished
✅ Buoyancy and stability tests approved
✅ Port Captaincy certification renewed
✅ Vessel returned to operation immediatelyACHIEVED RESULTS
✅ Early completion: 6 months turned into 5 months and 16 days
✅ Zero accidents: In complex naval environment works
✅ Certified quality: Port Captaincy approval without reservations
✅ Positive social impact: Ferry resumed operation before November (start of high season)
✅ Public recognition: Government and DERSA highlighted efficiency
QUANTITATIVE DATA
Plating replaced: 20+ tons of naval steel
Team (peak): 20 simultaneous professionals
Duration: 6 months (completed in 5.8 months)
Welds executed: 300+ linear meters
Painted area: 800+ m² (entire hull)
Work hours: 14,400 man-hours
Rework rate: <2%
Accidents: 0
Ferry capacity: 20-25 vehicles/trip
Location: Cananéia Channel (South Coast SP)
LASTING IMPACT
The refurbishment of the FB-16 allowed the vessel to return to operation and continue serving for many subsequent years, transporting thousands of vehicles and hundreds of thousands of people between Cananéia and Ilha Comprida.
This project consolidated our experience in the naval segment and demonstrated our ability to execute complex works in remote locations, under deadline pressure and with high public visibility – characteristics that would become a trademark of the Engport Group in the following years.
The FB-16 became part of the DERSA Coastal Ferry Modernization Program initiated in 2011, operating in conjunction with the FB-12 on the Cananéia/Ilha Comprida ferry route, which transports more than 8,000 vehicles per day during peak season.