ETM Reform - Pronave Group

← Back to Projects
Group Pronave Industrial
ETM Reform - Pronave Group
  • Client: Pronave Group
  • Location: São Sebastião, SP
  • Period: 2020 (2 months)
  • Category: INDUSTRIAL
Contact Us
 
  SPECIAL CONTEXT Engport's Director was Pronave Group's Operational Director years before and was involved in the original development of the ETM. Deep knowledge of the equipment.   WHAT IS ETM? ETM (Hopper) acts as an intermediate lung in the movement of bulk solids:
  • Ships unload at the top with the help of grabs
  • Material is temporarily stored
  • Gate releases for trucks
  THE PROBLEM 5+ years of uninterrupted operation:
  • Advanced corrosion in the structure
  • Gate with critical wear
  • Compromised sealing systems
  TRUST "Engport, you know this ETM - helped develop it. Needs refurbishment. Can you do it?" "We can. I'll return it better than new."   EXECUTION 2 teams in shifts for 2 months:
  1. Disassembly and inspection (1 week)
  2. Structural recovery (4 weeks)
  3. Finishing (2 weeks)
  4. Testing and commissioning (1 week)
RESULTS ✅ 2 months completed ✅ Zero accidents ✅ Operating perfectly to this day (2020-2025) ✅ Strengthened relationship   DATA
  • Type: ETM (Hopper) for bulk materials
  • Teams: 2 on rotation
  • Duration: 2 months
  • Structure: Dozens of tons
  • Status: Operating (2020-2025)

Your project demands absolute reliability. Engport delivers.

Certified team (ISO 9001, IRATA, AWS), a track record of 150+ delivered projects, and the ability to operate in critical environments with Zero Downtime. If you are looking for a flawless, on-time, fully traceable solution, talk to our engineering team.