Grab Recovery 13m³ - Natrios

← Back to Projects
Natrios Porto
Grab Recovery 13m³ - Natrios
  • Client: Natrios
  • Location: São Sebastião, SP (grab came from Recife, PE)
  • Period: 2021 (3 months)
  • Category: PORT EQUIPMENT
Contact Us

THE CATASTROPHIC ACCIDENT

13m³ grab operating in Recife: steel cable broke, equipment fell from 15 meters. Severe damages:

  • Deformed and cracked structure
  • Destroyed hydraulic system
  • Bent jaws
  • Twisted axles

Initial assessment: "Irrecoverable. Buy new."

THE CONFIDENCE

Engport's Director has a personal history with Natrios. Client asked: "Can you recover it?"

Response: "It's recoverable."

METHODOLOGY

3 simultaneous teams for 3 months:

Team 1 - Structure:

  • Straightening (hydraulic presses)
  • Cutting and replacing irreparable sections
  • Welding reinforcements
  • NDT on critical welds

Team 2 - Hydraulic:

  • Complete disassembly
  • Cylinder reconditioning
  • Replacement of hoses/connections
  • Pressure tests

Team 3 - Finishing:

  • Blasting Sa 2½
  • Marine anti-corrosive painting

Reused: 70% (structure, axles, motor, pumps)
Replaced: 30% (sheet metal, cylinders, hoses, electrical)

RESULTS

✅ 60-70% savings vs. new
✅ 3 months (much faster than importing)
✅ Certified for operation
✅ Operating perfectly to this day (4+ years)
✅ Market impact → Fullport

DATA

  • Type: Grab Smag Peiner 13m³
  • Damages: ~80% compromised
  • Teams: 3 simultaneous
  • Duration: 3 months
  • Recovery: 70%
  • Savings: 60-70%
  • Status: Operating (2021-2025)

Your project demands absolute reliability. Engport delivers.